Barge accident dents Deepwater wind farm foundation

Providence Journal|Alex Kuffner|Jul 31, 2015
Rhode IslandOffshore WindSafety

First, it was the weather. Rough seas forced the Providence company to push back until last Sunday the installation of the first steel foundation for the five-turbine wind farm off Block Island. Now, Deepwater is dealing with a construction mishap. Earlier this week, one of the barges being used in the project hit the latticework “jacket” foundation that had been placed in the water and dented one of its four hollow, tubular legs.


As it works to build the first offshore wind farm in the nation, Deepwater Wind is experiencing the potential difficulties of marine construction.

First, it was the weather. Rough seas forced the Providence company to push back until last Sunday the installation of the first steel foundation for the five-turbine wind farm off Block Island.

Now, Deepwater is dealing with a construction mishap. Earlier this week, one of the barges being used in the project hit the latticework “jacket” foundation that had been placed in the water and dented one of its four hollow, tubular legs.

“This is the kind of thing that can happen in construction projects, especially those offshore,” Deepwater said in a statement on Thursday.

It’s unclear how the …

... more [truncated due to possible copyright]

As it works to build the first offshore wind farm in the nation, Deepwater Wind is experiencing the potential difficulties of marine construction.

First, it was the weather. Rough seas forced the Providence company to push back until last Sunday the installation of the first steel foundation for the five-turbine wind farm off Block Island.

Now, Deepwater is dealing with a construction mishap. Earlier this week, one of the barges being used in the project hit the latticework “jacket” foundation that had been placed in the water and dented one of its four hollow, tubular legs.

“This is the kind of thing that can happen in construction projects, especially those offshore,” Deepwater said in a statement on Thursday.

It’s unclear how the company will repair the foundation, which was set to be secured to the ocean floor with piles this week. But Deepwater is not describing it as a major problem. 

“Our flexible schedule provides us more than enough time to address things like bad weather or repairs such as this one, so our timeline remains on-track,” the company said.

Installation of the foundations is supposed to take eight weeks and would wrap up in mid- to late-September. Offshore work would pick up again next year when the wind turbines are put in place.

Last week, because of the choppy waters off Block Island, Deepwater was forced to tow the barge carrying the first set of foundation sections to a pier off the Quonset Business Park in North Kingstown to do preliminary rigging work that couldn’t be done at sea.

After the work was completed, the barge was taken back to the location of the wind farm on Saturday and by the next day the waters were calm enough for the foundation to be lowered by a crane onto the ocean bottom.

It came just in time for a previously-scheduled boat tour on Monday of the project site for U.S. Interior Secretary Sally Jewell, Gov. Raimondo and other elected leaders and state officials. Although the skies were overcast, the waters were relatively flat during the trip.

But tough weather conditions are expected to return in the coming days. So installation of the second foundation won’t begin until the weather clears, Deepwater said.

 


Source:http://www.providencejournal.…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2026 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION